AIThis post was created with the assistance of artificial intelligence (AI).

TL;DR

Massachusetts is pursuing 5 gigawatts of battery storage by 2030 and 10 GW by 2035, supported by incentives, new permitting rules and utility procurements. More than 1.6 GW is already installed, but high grid-connection costs could slow projects.

Massachusetts is targeting 5 gigawatts of battery storage by 2030 and 10 GW by 2035, while using incentives, streamlined permitting and utility procurements to encourage construction. The state already has more than 1.6 GW installed, but expensive grid connections remain a significant obstacle for proposed projects.

Before you orderOffer from Amazon

Get backup power and energy gear delivered free with Prime

  • Fast, free delivery on millions of items
  • Prime Video, Amazon Music and more included
  • Member-only deals all year
Start your free Prime trial Free trial for eligible customers · Cancel anytime
As an affiliate, we earn on qualifying purchases.

The state’s buildout is moving beyond targets on paper. Near Boston, Jupiter Power is preparing the 700-megawatt Trimount project, with construction scheduled to begin next year. Another company has secured $850 million in financing for a 250-MW battery, while a 200-MW project near the Rhode Island border has broken ground and is expected to be operating by the end of the year, according to the source report. Several other projects are at different stages of development.

Massachusetts’ policy framework includes the Clean Peak Standard, which began in 2020 and pays renewable-energy facilities and storage owners for supplying electricity during periods of peak demand. The payments can add revenue for battery projects. The state also changed siting and permitting rules effective July 1: the Energy Facilities Siting Board can approve large energy projects, including storage facilities of at least 100 MW, and decisions are required within 15 months of an application.

The state is also using competitive procurements to secure storage capacity. In December 2025, it selected four projects totaling 1.3 GW to proceed to contract negotiations with major utilities. A second solicitation received 35 bids before closing earlier this month; project selections are expected in February. Selection for negotiations does not, by itself, mean that projects have completed contracting or construction.

At a glance
reportWhen: Targets set for 2030 and 2035; permitti…
The developmentMassachusetts is pairing its 10-GW battery storage target for 2035 with policies and procurement programs intended to bring more projects onto the grid.

How Batteries Could Affect Power Costs

Battery storage can shift electricity across time: operators can charge when power is abundant or less expensive, then discharge when demand rises. Massachusetts officials and advocates see that flexibility as useful in a state with high electricity prices and ambitious clean-energy goals. Storing surplus renewable generation may also reduce reliance on more expensive, emissions-intensive power during peak periods.

Storage can provide grid support, but it is not a substitute for generating electricity: batteries must first be charged, and their value depends on when they can charge and discharge. State Energy Resources Commissioner Elizabeth Mahony said storage can be deployed at different times to help manage system load. The projects’ actual effects on bills, emissions and reliability will depend on their costs, operation and connection to the grid.

The target also matters for project developers and utilities because it creates a longer-term signal about state demand for storage. But targets and policy incentives do not guarantee that every proposed facility will be built. Financing, permitting, utility contracts and interconnection costs all affect whether projects advance.

Products Worth Considering

Bose Home Speaker 500 Smart Bluetooth Speaker with Alexa, Black

Bose Home Speaker 500 Smart Bluetooth Speaker with Alexa, Black

As an affiliate, we earn on qualifying purchases.

From Early Storage Target to 10 GW

Massachusetts began its Energy Storage Initiative in 2015 under then-Gov. Charlie Baker. Its initial goal was to install 1 GW by 2025; the state exceeded that target, reaching more than 1.6 GW. The current plan calls for 5 GW by 2030, followed by another 5 GW by 2035.

The source report says 13 states have set storage procurement targets and describes Massachusetts’ 10-GW-by-2035 goal as the largest among them. That is a target comparison, not a claim that Massachusetts currently has the country’s most installed storage. California, for example, has about 23 GW installed, according to the report. Massachusetts’ approach combines its target with incentives, permitting changes and utility solicitations to support future projects.

“Massachusetts is really a leader in this space. We’re ahead of the pack as it relates to encouraging battery buildout.”

— Erin Smith, energy and grid policy director at the Environmental League of Massachusetts

Grid Connection Costs Remain Unsettled

Interconnection costs are a major unresolved constraint. Developers canceled a planned 125-MW battery in Tewksbury in September after citing a $65 million estimate for grid upgrades needed to connect it. A recent study by grid operator ISO New England found that estimated interconnection costs for a number of proposed projects—most of them batteries in Massachusetts—often exceeded $200 million, according to the source report.

Those estimates do not establish what every project will ultimately pay, and the source material does not provide the full study results or a final accounting of the projects’ connection costs. It is also unclear how many of the proposed facilities will reach construction, how quickly selected projects will complete utility contracts, or how the state’s targets will translate into operating capacity by each deadline.

February Selections and Project Approvals

The next stated procurement milestone is expected in February, when Massachusetts plans to announce which projects move forward from the solicitation that drew 35 bids. Selected projects would still need to proceed through the relevant contracting and development steps before they can be counted as operating storage.

Developers and officials will also have to work through the new siting process and project-specific grid connections. The state’s 15-month decision requirement applies to covered applications, but it does not remove the need for grid upgrades. Progress toward the 2030 and 2035 targets will depend on how many projects secure contracts, financing and affordable interconnection arrangements.

Key Questions

What battery-storage capacity is Massachusetts targeting?

The state aims to have 5 GW by 2030 and 10 GW by 2035. It had installed more than 1.6 GW, according to the source report.

What policies are meant to support new battery projects?

Support includes payments under the Clean Peak Standard, revised siting and permitting rules, and utility procurement solicitations for large storage projects.

How could batteries help electricity customers?

Batteries can store electricity when it is available and discharge it during periods of higher demand. State officials and advocates say this could help manage peak loads, but the source does not establish a specific bill reduction.

What is the main obstacle facing proposed projects?

Grid interconnection costs are a key concern. A planned 125-MW Tewksbury project was canceled after developers cited $65 million in required upgrades; estimates for many projects in an ISO New England study topped $200 million.

When will the state announce the next procurement selections?

Massachusetts is expected to announce selected projects in February from a solicitation that received 35 bids. Selection would be a step toward development, not confirmation that a project is operating.

Source: canarymedia.com

You May Also Like

Tesla Is Now Making More EVs That Can Double As A Home Battery

Tesla says new Model 3 and Model Y vehicles can power homes when paired with a Powerwall 3, using onboard hardware instead of a costly bidirectional charger.

Best Solar Backup Power Stations Compared

Compare portable solar power stations with whole-home battery systems by capacity, cost, outage coverage, installation, and best-fit use.

SoCal Edison Solar Export

Southern California Edison launches a new solar export initiative, allowing solar energy producers to send excess power to the grid. Details are still emerging.

5 Ballot Proposals That Could Drive Or Derail Clean Energy

A report examines five ballot proposals and their potential effects on clean energy, power costs and emissions. The proposals and their status are not identified in the supplied material.